Supply Chain Issues Create Backlog for Pool Installers - 27 East

Residence

Residence / 2021806

Supply Chain Issues Create Backlog for Pool Installers

icon 3 Photos
An inground pool produced by Pristine Pools on Briar Patch Road in East Hampton.
 COURTESY PRISTINE POOLS

An inground pool produced by Pristine Pools on Briar Patch Road in East Hampton. COURTESY PRISTINE POOLS

The Pristine Pools team excavates a backyard on July 20, 2022.
 COURTESY PRISTINE POOLS

The Pristine Pools team excavates a backyard on July 20, 2022. COURTESY PRISTINE POOLS

An above-ground pool built by Pristine Pools on Crescent Avenue in Water Mill. 
 COURTESY PRISTINE POOLS

An above-ground pool built by Pristine Pools on Crescent Avenue in Water Mill. COURTESY PRISTINE POOLS

Megan Naftali on Sep 14, 2022

As the temperature dwindles and the summer feeling disappears, pool season is coming to an end, but if you’re hoping to get the pool of your dreams installed by next season, the time to start planning is now — if it’s not too late already.

Supply shortages and delays have affected many industries amid the pandemic, and pool service and installation companies have not been spared. Pool contractors are finding it difficult to acquire the electronics and raw materials they need in a timely manner, leading to a backlog of pools to build, according to Greg Darvin, the founder and owner of Pristine Pools in East Hampton.

“Right now anything with electronics seems to be the biggest issue. So in my industry, that would be swimming pool pumps, swimming pool heaters and control systems,” Darvin said. “Then we’re also having issues with certain raw materials. Concrete at one point was a bit of a problem. That seems to have evened out, but a lot of different stone materials, the availability or the lead times are much longer and straight across the board.”

Jack Fried, a principal engineer at Brookhaven National Laboratory, said that a global chip shortage could be responsible for the electronic supply shortage. “Some of those electronics used in the pools do use chips so there might be shortages of those things,” he said.

Certain pool parts that don’t rely on a chip themselves could be delayed because the equipment to manufacturer them might be backordered or broken, he explained. “If anything in the supply chain is disrupted due to not having parts or chips to make it, everything gets delayed,” he said.

Fried added that a project he’s working on now requires a chip, but the wait time to receive the part is over 55 weeks.

The supply shortage has caused Darvin to change the way he plans to obtain the materials needed for pool production. For about 27 years, he did not stock materials and instead bought them as needed. Now Darvin tries to start sourcing and purchasing materials early and stock them until they become necessary.

“Logistics and planning have become much more important,” said Santo Buttafuoco, the pool construction manager at Pristine Pools. “In the past we were a bit spoiled but didn’t realize it. When material is always ‘readily available’ you don’t put as much value on it or the time it takes to order or replace the necessary items.”

Another way in which Pristine Pools tried to combat the supply shortage was by looking for substitutes. “If our preferred pump or light fixture is unavailable with no good information for restocking, we have had to test and source items from other competing manufacturers,” Buttafuoco said.

Darvin is open with potential clients regarding the current state of the pool production process, and as a contractor attempts to educate them during the decision-making process on the existing and possible challenges. “Even though it could add frustration, people seem to actually be reasonable and understanding about it,” he said.

Pristine Pools has been creating clients’ dream pools for about 30 years and continues to work through the challenges brought on by the supply shortage.

“As a whole, our company takes a tremendous amount of pride in our craft. We are much more interested in the quality rather than quantity, and this is something that starts from the top down,” Buttafuoco said. “Even though schedule is important, we understand that what we are building needs to stand the test of time to make our clients’ investments worthwhile.”

Designing, acquiring permits, excavating and installing the pool used to take a few months, but the shortage has extended the process. Potential clients now need to plan far in advance.

“If you want to have a completed pool project for next season and haven’t started the process, you may be too late,” Darvin said.

You May Also Like:

Spring Is the Time To Pot Up Houseplants

In spring our gardening attention logically and naturally focuses on things going on outside. We ... 25 Apr 2024 by Andrew Messinger

The April Ramble

April got off to a typical start. For most of the first two weeks of ... 18 Apr 2024 by Andrew Messinger

AIA Peconic Presents 2024 Design Awards

AIA Peconic, the East End’s chapter of the American Institute of Architects, recognized outstanding design, ... 15 Apr 2024 by Brendan J. O’Reilly

A Complicated Task – The Renovation and Addition to Temple Adas Israel

For any architect, the renovation and addition to a temple like Adas Israel would be ... by Anne Surchin, R.A.

Plant Radishes Now

As you may have discovered from last week’s column there is more to a radish ... 11 Apr 2024 by Andrew Messinger

In Praise of Trees

“The best time to plant a tree was 20 years ago. The next best time ... 9 Apr 2024 by Marissa Bridge

PSEG Reminds Customers To Call 811 Before Digging

As National Safe Digging Month begins, PSEG Long Island reminds customers, contractors and excavators that the law requires them to call 811 before digging to ensure underground pipelines, conduits, wires and cables are properly marked out. Striking an underground electrical line can cause serious injury and outages, resulting in repair costs and fines, PSEG stated in an announcement this week. Every digging project, even a small project like planting a tree or building a deck, requires a call to 811. The call is free and the mark-out service is free. The call must be made whether the job is being ... by Staff Writer

Capturing the Artistry of Landscape Architecture

Pink and white petals are unfolding from their fuzzy bud scales, hyacinths scent the air ... by Kelly Ann Smith

AIA Peconic To Hold Design Awards Celebration April 13 in East Hampton

AIA Peconic, the East End’s chapter of the American Institute of Architects, will hold its 2024 Daniel J. Rowen Memorial Design Awards celebration on Saturday, April 13, at 6 p.m. at the Ross School Senior Lecture Hall in East Hampton. The work submitted to the Design Awards will be on gallery display. The jurors included Deborah Burke, Joeb Moore and Omar Gandhi, and the special jury adjudicating the Sustainable Architecture Award: Anthony Harrington, Whitney Smith and Rives Taylor. The awards presentation will include remarks by AIA Peconic President Edgar Papazian and a program moderated by past AIA Peconic President Lori ... 4 Apr 2024 by Staff Writer

A Brief History of Radishes

The madness will begin. Adventurous souls have had just one day too many of cabinus ... by Andrew Messinger